Risk Based Assessment Framework (RBAF)

FFA consequence scores submitted date: Jul 2021
EU consequence scores submitted date: Jul 2022
PH consequence scores submitted date: Nov 2021
Obligation Category When Evaluated Average Score (%) Likelihood
European Union
Consequence
Risk
FFA
Consequence
Risk
Philippines
Consequence
Risk
CMM 2004-03 02 Implementation 2013, 2016 96 Unlikely Serious High Major High Major High
CMM 2004-03 03 Implementation 2013 96 Unlikely Major High Major High Major High
CMM 2005-03 03 Report 2013, 2015, 2016, 2017, 2018 97 Unlikely
CMM 2005-03 03 Report Deadline 2013, 2015, 2016, 2016, 2018 88 Moderate
CMM 2006-04 01 Quantitative Limits: CCM-level and Collective 2013, 2020, 2021, 2022 100 Rare Serious High Serious High Major Moderate
CMM 2006-04 04 Report 2013, 2020, 2021, 2022 94 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2006-08 07 Implementation 2013, 2014, 2015 99 Unlikely Serious High Major High Major High
CMM 2006-08 30 and 32 Implementation 2013, 2014, 2015 87 Moderate Major High Moderate Moderate Moderate Moderate
CMM 2006-08 30 and 32 Report Deadline 2013, 2014, 2015 95 Unlikely Major High Moderate Moderate Moderate Moderate
CMM 2006-08 32 Implementation 2013, 2015 100 Rare Serious High Major Moderate Major Moderate
CMM 2006-08 33 and 36 Implementation 2013, 2015 100 Rare Serious High Major Moderate Major Moderate
CMM 2006-08 33 and 36 Report Deadline 2013, 2015 84 Moderate Serious Severe Major High Major High
CMM 2006-08 40 Implementation 2013, 2014, 2015 92 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2006-08 40 Report Deadline 2013, 2014, 2015 92 Moderate Minor Moderate Minor Moderate Moderate Moderate
CMM 2006-08 41 Implementation 2013, 2014, 2015 92 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2006-08 41 Report Deadline 2013, 2014, 2015 83 Moderate Minor Moderate Minor Moderate Moderate Moderate
CMM 2008-03 07c Report 2013, 2015 94 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2008-03 07c Report Deadline 2013, 2015 94 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2008-04 02 Implementation Moderate Serious Severe Major High Major High
CMM 2008-04 05 Report 2015 95 Unlikely Minor Low Moderate Moderate Moderate Moderate
CMM 2008-04 05 Report Deadline 2013, 2015 82 Moderate Minor Moderate Minor Moderate Moderate Moderate
CMM 2009-02 03-07 Implementation 2013 94 Moderate
CMM 2009-02 08-12 Report 2013 100 Rare
CMM 2009-02 08-12 Report Deadline 2013 100 Rare
CMM 2009-02 08-13 Quantitative Limits: CCM-level and Collective 2013 100 Rare
CMM 2009-03 01 Quantitative Limits: CCM-level and Collective 2013, 2014, 2016, 2020, 2021, 2022 98 Unlikely Serious High Major High Major High
CMM 2009-03 02 Quantitative Limits: CCM-level and Collective 2013, 2014, 2016, 2020, 2021, 2022 97 Unlikely Serious High Major High Major High
CMM 2009-03 03 Quantitative Limits: CCM-level and Collective 2013, 2014, 2016 97 Unlikely Serious High Major High Major High
CMM 2009-03 03 Implementation 2020, 2021, 2022 100 Rare
CMM 2009-03 08 Report 2013, 2014, 2016, 2020, 2021, 2022 99 Unlikely Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2009-03 08 Report Deadline 2013, 2014, 2016 88 Moderate Minor Moderate Minor Moderate Moderate Moderate
CMM 2009-05 01, 03, 05 Implementation Moderate Major High Major High Major High
CMM 2009-06 11 Report 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 84 Moderate Moderate Moderate Major High Major High
CMM 2009-06 11 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 81 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2009-06 13 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020 95 Unlikely Serious High Major High Major High
CMM 2009-06 29 Quantitative Limits: CCM-level and Collective 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 100 Rare Serious High Major Moderate Major Moderate
CMM 2009-06 34 Quantitative Limits: CCM-level and Collective 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 90 Moderate Serious Severe Major High Major High
CMM 2009-06 35 a (ii) Report 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 95 Unlikely Serious Severe Major High Major High
CMM 2009-06 35 a (iii) Report 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 79 Likely Serious Severe Major Severe Major Severe
CMM 2009-06 35 a (iii) Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 26 Almost Certain Serious Severe Major Severe Moderate Severe
CMM 2009-06 35 a (iv) Report 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 83 Moderate Major High Major High Moderate Moderate
CMM 2009-06 35 a (iv) Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 33 Almost Certain Minor High Minor High Minor High
CMM 2009-06 35 a (v) Report Moderate Minor Moderate Moderate Moderate Moderate Moderate
CMM 2009-09 05 Report Moderate Serious Severe Moderate Low Major High
CMM 2010-01 05 Quantitative Limits: CCM-level and Collective 2013, 2014, 2016, 2017, 2018, 2019, 2020, 2021, 2022 97 Unlikely Serious High Major High Major High
CMM 2010-01 08 Report 2014, 2016, 2017, 2018, 2019, 2020 100 Rare Moderate Low Moderate Low Minor Low
CMM 2010-01 08 Report Deadline 2013, 2014 79 Likely Moderate High Minor Moderate Minor Moderate
CMM 2010-02 02 Report 2013, 2014, 2015, 2016 62 Likely
CMM 2010-02 02 Report Deadline 2013, 2014, 2015, 2016 32 Almost Certain
CMM 2010-02 06 Report 2013 100 Rare
CMM 2010-07 06 Quantitative Limits: CCM-level and Collective 2016 100 Rare
CMM 2010-07 07 Quantitative Limits: CCM-level and Collective 2013 85 Moderate
CMM 2011-03 01 Quantitative Limits: CCM-level and Collective 2016 100 Rare Serious High Major Moderate Major Moderate
CMM 2011-03 01 Implementation 2021, 2022 98 Unlikely Serious High Major High Major High
CMM 2011-03 02 Implementation Moderate Serious Severe Moderate Moderate Major High
CMM 2011-03 03 Implementation Moderate Moderate Moderate Moderate Moderate Major High
CMM 2011-03 05 Report 2013, 2016 90 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2011-03 05 Report Deadline 2013, 2016 71 Likely Minor Moderate Minor Moderate Moderate High
CMM 2011-04 01 Implementation 2018, 2019 97 Unlikely
CMM 2011-04 03 Report 2013, 2015, 2017, 2018, 2019 91 Moderate
CMM 2011-04 03 Report Deadline 2013, 2015, 2017, 2018, 2019 88 Moderate
CMM 2012-01 28 Report 2013 91 Moderate
CMM 2012-01 28 Report Deadline 2013 73 Likely
CMM 2012-03 02 Quantitative Limits: CCM-level and Collective Likely Serious Severe Major Severe Moderate High
CMM 2012-04 01 Quantitative Limits: CCM-level and Collective 2016 100 Rare
CMM 2012-04 01 Implementation 2020 95 Unlikely
CMM 2013-01 28 Quantitative Limits: CCM-level and Collective 2014 100 Rare
CMM 2013-05 01 Report 2015, 2016 98 Unlikely Serious High Major High Major High
CMM 2013-05 02 Report 2015, 2016 98 Unlikely Serious High Major High Major High
CMM 2013-05 03 Implementation Moderate Major High Major High Moderate Moderate
CMM 2013-05 04 Implementation Moderate Serious High Major High Moderate Moderate
CMM 2013-07 19 Report Likely Moderate High Major Severe Moderate High
CMM 2013-07 19 Report Deadline 2015, 2016 52 Likely Moderate High Major Severe Moderate High
CMM 2013-08 01 Quantitative Limits: CCM-level and Collective 2015, 2017 91 Moderate
CMM 2013-08 01 Implementation 2018, 2019 97 Unlikely
CMM 2013-08 03 Report 2015, 2017, 2018, 2019 97 Unlikely
CMM 2013-08 03 Report Deadline 2015, 2017, 2018, 2019 95 Unlikely
CMM 2014-02 04 Implementation 2013, 2014, 2015, 2016, 2017 99 Unlikely Serious High Major High Major High
CMM 2014-02 9a Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 82 Moderate Serious Severe Major High Major High
CMM 2014-02 9a VMS SSPs 2.1.3 and 7.2.2 Report 2018, 2019, 2020 99 Unlikely Moderate Moderate Moderate Low Moderate Moderate
CMM 2014-02 9a VMS SSPs 2.1.3 and 7.2.2 Implementation 2013, 2014, 2015, 2016, 2017 97 Unlikely Moderate Moderate Moderate Low Moderate Moderate
CMM 2014-02 9a VMS SSPs 2.1.3 and 7.2.2 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 85 Moderate Moderate Moderate Moderate Low Moderate Moderate
CMM 2014-02 9a VMS SSPs 2.8 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021 92 Moderate Serious Severe Major High Major High
CMM 2014-02 9a VMS SSPs 2.8 Report 2022 100 Serious Major Major
CMM 2014-02 9a VMS SSPs 5.4 - 5.5 Implementation 2013 100 Rare Serious High Moderate Low Moderate Low
CMM 2014-02 9a VMS SSPs 5.4 - 5.5 Report Deadline 2013 100 Rare Serious High Moderate Low Moderate Low
CMM 2014-02 9a VMS SSPs 7.2.4 Implementation 2013 100 Rare Minor Low Moderate Low Major Moderate
CMM 2014-02 9a VMS SSPs 7.2.5 Implementation 2013 100 Rare Moderate Low Moderate Low Moderate Low
CMM 2014-03 02 Implementation 2014, 2015, 2016 50 Likely Moderate High Minor Moderate Moderate High
CMM 2014-05 02 Report Moderate
CMM 2015-01 37 Implementation 2013 94 Moderate
CMM 2015-02 01 Quantitative Limits: CCM-level and Collective 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020 96 Unlikely Serious High Major High Moderate Moderate
CMM 2015-02 04 Report 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 99 Unlikely Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2015-04 03 Quantitative Limits: CCM-level and Collective 2013, 2014, 2015, 2016 90 Moderate
CMM 2015-07 36 (7, 11) Report 2016 88 Moderate
CMM 2015-07 36 (7, 11) Report Deadline 2014 83 Moderate
CMM 2016-01 16 Report 2013 89 Moderate
CMM 2016-01 16 Quantitative Limits: CCM-level and Collective 2016, 2017 100 Rare
CMM 2016-01 16 Implementation 2013, 2014, 2015, 2016, 2017 96 Unlikely
CMM 2016-01 16 Report Deadline 2013, 2014, 2015, 2016, 2017 59 Likely
CMM 2016-01 16 footnote 3 Report Deadline 2014, 2015, 2016, 2017 46 Almost Certain
CMM 2016-01 18 Quantitative Limits: CCM-level and Collective 2017 100 Rare
CMM 2016-01 18 Implementation 2017 100 Rare
CMM 2016-01 19 Report 2013, 2014, 2015, 2016, 2017 95 Unlikely
CMM 2016-01 19 Report Deadline 2013 33 Almost Certain
CMM 2016-01 24 Report 2014, 2015, 2016, 2017 94 Moderate
CMM 2016-01 24 Quantitative Limits: CCM-level and Collective 2014, 2015, 2016, 2017 75 Likely
CMM 2016-01 24 Report Deadline 2014, 2015, 2016, 2017 72 Likely
CMM 2016-01 37 Implementation 2014, 2015, 2016, 2017 100 Rare
CMM 2016-01 37 Report Deadline 2014, 2015, 2016, 2017 99 Unlikely
CMM 2016-01 48 Report 2013, 2014, 2015, 2016, 2017 82 Moderate
CMM 2016-02 06 Quantitative Limits: CCM-level and Collective 2020 96 Unlikely Major High Moderate Moderate Major High
CMM 2017-01 29 Report 2018 100 Rare Serious
CMM 2017-01 46 Report 2016, 2017 100 Rare Serious
CMM 2017-01 46 Quantitative Limits: CCM-level and Collective 2014, 2015 100 Rare Serious
CMM 2017-01 46 Report Deadline 2014, 2015 100 Rare Serious
CMM 2017-02 02 (b) Implementation Serious Major High
CMM 2017-02 06 Report Serious Moderate Moderate
CMM 2017-02 08 Report Serious Major High
CMM 2017-02 09-10 Report Serious Major High
CMM 2017-02 11-12 Implementation Serious Moderate Moderate
CMM 2017-02 13-14 Report Serious Moderate Moderate
CMM 2017-02 16 Implementation Serious Moderate Moderate
CMM 2017-02 17 Report Serious Major High
CMM 2017-02 19 and 21 Report Serious Moderate Moderate
CMM 2017-02 20 Implementation Serious Moderate Moderate
CMM 2017-02 21 Report Moderate Moderate Moderate
CMM 2017-02 22 Implementation Serious Moderate Moderate
CMM 2017-02 23-24 Implementation Moderate Moderate
CMM 2017-02 26 Report Moderate Moderate
CMM 2017-02 27 Report Serious Moderate Moderate
CMM 2017-03 03-06 Report Moderate Serious Severe Serious Severe Serious Severe
CMM 2017-03 07-08 Report Moderate Serious Severe Serious Severe Serious Severe
CMM 2017-03 09 Report Moderate Moderate Moderate Moderate Moderate Major High
CMM 2017-03 10 Report Moderate Major High Major High Major High
CMM 2017-03 11 Report Moderate Serious Severe Major High Serious Severe
CMM 2017-03 12 Report Moderate Serious Severe Serious Severe Moderate Moderate
CMM 2017-04 02 Implementation 2020 100 Rare Serious Severe Major Severe Major High
CMM 2017-04 08 Implementation Moderate Major High
CMM 2017-04 08 Report Moderate Moderate Moderate Moderate
CMM 2017-06 04 Report 2013 91 Moderate
CMM 2017-06 04 Report Deadline 2013 91 Moderate
CMM 2018-03 01 Implementation 2020 88 Moderate Serious Severe Major High Moderate Moderate
CMM 2018-03 01, 02, 06 Implementation Moderate Serious Severe Major High Moderate Moderate
CMM 2018-03 02 Implementation 2020 89 Moderate Serious Severe Major High Moderate Moderate
CMM 2018-03 06 Implementation 2020 83 Moderate Serious Severe Major High Moderate Moderate
CMM 2018-03 08 Report 2015, 2016 100 Rare Major Moderate Moderate Low Moderate Low
CMM 2018-03 08 Report Deadline 2015, 2016 100 Rare Moderate Low Minor Low Moderate Low
CMM 2018-03 13 Report 2013, 2015, 2016 93 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2018-03 13 Report Deadline 2013, 2015, 2016 83 Moderate Moderate Moderate Minor Moderate Moderate Moderate
CMM 2018-04 02 and 03 Report 2013, 2015 93 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2018-04 02 and 03 Report Deadline 2013, 2015 91 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2018-04 04 Report Moderate Serious Severe Moderate Moderate Major High
CMM 2018-04 05 (a-d) Report Moderate Major Moderate Moderate Moderate Moderate Moderate
CMM 2018-04 05a Implementation 2020 90 Moderate Serious Severe Minor Moderate Moderate Moderate
CMM 2018-04 06 Implementation 2020, 2021, 2022 98 Unlikely Major High Major High Major High
CMM 2018-04 07 (a, b) Implementation 2020, 2021, 2022 100 Rare Serious High Major Moderate Moderate Low
CMM 2018-04 07 (d, e) Report Moderate Major Moderate Moderate Moderate Moderate Moderate
CMM 2018-04 07c Report 2013, 2015 94 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2018-04 07c Report Deadline 2013, 2015 94 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2018-05 07 Implementation 2013, 2014, 2015, 2016 99 Unlikely Serious High Major High Major High
CMM 2018-05 08 Implementation 2014 100 Rare
CMM 2018-05 09 Implementation 2013, 2014 92 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2018-05 10 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020 99 Unlikely Moderate Moderate Major High Moderate Moderate
CMM 2018-05 11 Report Moderate Serious Severe Major High Major High
CMM 2018-05 14 Implementation 2014, 2015, 2016 98 Unlikely Minor Low Moderate Moderate
CMM 2018-05 14 Report Unlikely Minor Moderate Moderate
CMM 2018-05 15 (g) Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020 94 Moderate Moderate Moderate Serious Severe Major High
CMM 2018-05 Annex C 04 Quantitative Limits: CCM-level and Collective 2013, 2014 100 Rare
CMM 2018-05 Annex C 04 Implementation 2013, 2014 100 Rare Minor Low Major Moderate Moderate Low
CMM 2018-05 Annex C 06 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019 64 Likely Serious Severe Major Severe Major Severe
CMM 2018-05 Annex C 06 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 84 Moderate Major High Major High
CMM 2018-05 Annex C 08 Implementation 2014 100 Rare Moderate Low Moderate Low Major Moderate
CMM 2018-06 02 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019 98 Unlikely Serious High Serious High Serious High
CMM 2018-06 03 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019 98 Unlikely Serious High Serious High Serious High
CMM 2018-06 04 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019 99 Unlikely Serious High Major High Major High
CMM 2018-06 07 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019 99 Unlikely Major High Major High Moderate Moderate
CMM 2018-06 07 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 99 Unlikely Major High Major High Moderate Moderate
CMM 2018-06 09 Report 2018, 2019, 2020, 2021, 2022 99 Unlikely Serious High Minor Low Moderate Moderate
CMM 2018-06 09 Implementation 2013, 2014, 2015, 2016, 2017 98 Unlikely
CMM 2018-06 09 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 96 Unlikely Moderate Moderate Minor Low Moderate Moderate
CMM 2018-06 11 Report Unlikely Minor Low Minor Low Major High
CMM 2018-06 16 Implementation 2014, 2015, 2016 98 Unlikely Serious High Moderate Moderate Moderate Moderate
CMM 2018-06 17 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019 99 Unlikely Serious High Major High Major High
CMM 2018-06 18 Implementation 2013 97 Unlikely Serious High Major High Major High
CMM 2019-03 02 Quantitative Limits: CCM-level and Collective 2013, 2014, 2015, 2017, 2018, 2019, 2020 97 Unlikely Serious High Major High Major High
CMM 2019-03 03 Report 2013, 2014, 2015, 2017, 2018, 2019, 2020 99 Unlikely Major High Moderate Moderate Moderate Moderate
CMM 2019-03 03 Report Deadline Moderate Moderate Moderate Minor Moderate Moderate Moderate
CMM 2019-04 05 Report 2020, 2021, 2022 96 Unlikely Major High Moderate Moderate Moderate Moderate
CMM 2019-04 05 Report Deadline 2013, 2015, 2016, 2017, 2018, 2019 92 Moderate
CMM 2019-04 07-10 Implementation 2021, 2022 97 Unlikely Serious High Major High Major High
CMM 2019-04 07-10 Report Deadline Moderate Serious High Major High Major High
CMM 2019-04 11 Report 2021, 2022 97 Unlikely Major High Moderate Moderate Moderate Moderate
CMM 2019-04 11 Report Deadline 2021, 2022 87 Moderate Moderate Moderate Minor Moderate Moderate Moderate
CMM 2019-04 12 Quantitative Limits: CCM-level and Collective 2013, 2015, 2016, 2017 91 Moderate
CMM 2019-04 12 Implementation 2018, 2019, 2020, 2021, 2022 99 Unlikely Serious High Major High Moderate Moderate
CMM 2019-04 13 Implementation 2021, 2022 99 Unlikely Serious High Major High Major High
CMM 2019-04 14-15 Implementation 2021, 2022 100 Rare Serious High Moderate Low Major Moderate
CMM 2019-04 14-15 Report Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2019-04 16 Implementation 2021 100 Rare Moderate Low Moderate Low Moderate Low
CMM 2019-04 16 Report 2022 100 Rare Moderate Low Moderate Low Moderate Low
CMM 2019-04 16 Report Deadline 2016 100 Rare Moderate Low Minor Low Moderate Low
CMM 2019-04 18 Implementation 2021, 2022 90 Moderate Major High Moderate Moderate Major High
CMM 2019-04 20 (01) Implementation 2021, 2022 99 Unlikely Serious High Serious High Major High
CMM 2019-04 20 (02) Implementation 2021, 2022 97 Unlikely Serious High Serious High Major High
CMM 2019-04 20 (03) Implementation 2021, 2022 93 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2019-04 20 (04) Report Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2019-04 21 (01-07) Implementation 2021, 2022 94 Moderate Serious Severe Serious Severe Major High
CMM 2019-04 21 (04) Report 2016, 2021, 2022 100 Rare Serious High Moderate Low Major Moderate
CMM 2019-04 21 (04) Report Deadline 2016 100 Rare
CMM 2019-04 23 Report 2021, 2022 100 Rare Major Moderate Moderate Low Moderate Low
CMM 2019-04 23 Report Deadline 2021, 2022 100 Rare Moderate Low Moderate Low Moderate Low
CMM 2019-05 (04-06, 08, 10) Implementation 2021, 2022 78 Likely Serious Severe Moderate High Major Severe
CMM 2019-05 03 Implementation Moderate Serious Severe Major High Major High
CMM 2019-06 17 Report Deadline 2013 84 Moderate
CMM 2019-06 45 Report Deadline 2013 84 Moderate
CMM 2019-07 22 Implementation 2016 97 Unlikely Serious Severe Major High Major High
CMM 2020-02 03 Implementation 2020 100 Rare
CMM 2021-01 14 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 94 Moderate Serious Severe Major High Major High
CMM 2021-01 15 Report 2018, 2019, 2020, 2021, 2022 100 Rare Moderate Low Moderate Low Moderate Low
CMM 2021-01 15 Implementation 2021, 2022 98 Unlikely Serious High Major High Moderate Moderate
CMM 2021-01 15 Report Deadline 2018, 2019 85 Moderate Moderate Moderate Moderate Moderate Moderate Moderate
CMM 2021-01 15 Implementation 2018, 2019, 2020, 2021, 2022 98 Unlikely Serious High Major High Moderate Moderate
CMM 2021-01 17 Implementation Moderate Serious Severe Moderate Moderate Major High
CMM 2021-01 21 Implementation 2018, 2019, 2020 100 Rare Serious High Major Moderate Major Moderate
CMM 2021-01 24 Quantitative Limits: CCM-level and Collective 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 94 Moderate Serious Severe Serious Severe Moderate Moderate
CMM 2021-01 24 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 79 Likely Moderate High Moderate High Moderate High
CMM 2021-01 25 Quantitative Limits: CCM-level and Collective 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 92 Moderate Serious Severe Serious Severe Major High
CMM 2021-01 26 Quantitative Limits: CCM-level and Collective 2013, 2014 100 Rare
CMM 2021-01 26 Implementation 2018, 2019, 2020 100 Rare Moderate Low Minor Low Moderate Low
CMM 2021-01 29 Report 2016, 2017, 2018 100 Rare
CMM 2021-01 29 Quantitative Limits: CCM-level and Collective 2013, 2014, 2015 100 Rare
CMM 2021-01 29 Implementation 2019, 2020 100 Rare Major Moderate Moderate Low Major Moderate
CMM 2021-01 31 Quantitative Limits: CCM-level and Collective 2013 100 Rare
CMM 2021-01 31 Implementation 2013, 2018, 2019, 2020 100 Rare Major Moderate Moderate Low Moderate Low
CMM 2021-01 32 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020 97 Unlikely Serious High Serious High Serious High
CMM 2021-01 33 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020 88 Moderate Serious Severe Serious Severe Serious Severe
CMM 2021-01 37 Quantitative Limits: CCM-level and Collective 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 95 Unlikely Serious High Serious High Major Moderate
CMM 2021-01 38 Report 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 91 Moderate Major High Major High Moderate Moderate
CMM 2021-01 38 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 50 Likely Moderate High Moderate High Moderate High
CMM 2021-01 40 Quantitative Limits: CCM-level and Collective 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 100 Rare Serious High Major Moderate Major Moderate
CMM 2021-01 42 Quantitative Limits: CCM-level and Collective 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 100 Rare Serious High Major Moderate Major Moderate
CMM 2021-01 44 Quantitative Limits: CCM-level and Collective 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 100 Rare Serious High Major Moderate Major Moderate
CMM 2021-01 45 Quantitative Limits: CCM-level and Collective 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 100 Rare Serious High Major Moderate Major Moderate
CMM 2021-01 47 Quantitative Limits: CCM-level and Collective 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020 97 Unlikely Serious High Moderate Moderate Moderate Moderate
CMM 2021-01 48 Report 2016, 2017, 2018, 2019, 2020 100 Rare Major Moderate Major Moderate Major Moderate
CMM 2021-01 48 Report Deadline 2014 80 Moderate
CMM 2021-01 50 Report 2016, 2017, 2018, 2019, 2020 100 Rare Major Moderate Major Moderate Major Moderate
CMM 2021-01 50 Report Deadline 2014 100 Rare
CMM 2021-01 Att 2 03 Report 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 50 Likely Moderate High Moderate High Moderate High
CMM 2021-01 Att 2 03 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 14 Almost Certain Moderate Severe Moderate Severe Moderate Severe
CMM 2021-01 Att 2 04 Report 2014, 2015 50 Likely Moderate High Minor Moderate Major Severe
CMM 2021-01 Att 2 05-06 Implementation 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 100 Rare Serious High Major Moderate Major Moderate
CMM 2021-01 Att 2 08 Report 2014, 2015, 2016, 2017 100 Rare
CMM 2021-01 Att 2 08 Implementation 2018, 2019, 2020 100 Rare Serious High Moderate Low Major Moderate
CMM 2021-02 02 Quantitative Limits: CCM-level and Collective 2017, 2018, 2019, 2020, 2021, 2022 100 Rare Serious High Serious High Major Moderate
CMM 2021-02 03 Quantitative Limits: CCM-level and Collective 2017, 2018, 2019, 2020, 2021, 2022 98 Unlikely Serious High Serious High Major High
CMM 2021-02 04 Quantitative Limits: CCM-level and Collective 2016, 2017, 2018, 2019, 2022 96 Unlikely Serious High
CMM 2021-02 04 Implementation 2020, 2021 100 Rare Serious High
CMM 2021-02 08 Report 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 100 Rare Major Moderate Major Moderate Moderate Low
CMM 2021-02 08 Report Deadline 2015 100 Rare Moderate Low Major Moderate Moderate Low
CMM 2021-02 10 Report Moderate Minor Moderate Major High Moderate Moderate
CMM 2021-02 11 Report Moderate Major High Major High Major High
CMM 2021-02 13 Report Moderate Moderate Moderate Major High Moderate Moderate
CMM 2021-02 14 Report 2013, 2014, 2015, 2017, 2018, 2019, 2020, 2021, 2022 100 Rare Moderate Low Major Moderate Moderate Low
CMM 2021-02 14 Report Deadline 2013, 2014, 2015, 2016 82 Moderate Moderate Moderate Major High Moderate Moderate
CMM 2021-03 17 Report Moderate Major High Moderate Moderate Moderate Moderate
CMM 2021-03 45 Report Moderate Major High Major High Major High
CMM 2021-04 02 Report 2019, 2020, 2021, 2022 89 Moderate Major High Moderate Moderate Major High
CMM 2021-04 02 Report Deadline 2019 30 Almost Certain Major Severe Moderate Severe Moderate Severe
CMM 2021-04 03 Report 2019, 2020 100 Rare Major Moderate Moderate Low Moderate Low
CMM 2021-04 03 Report Deadline 2013, 2016, 2019 79 Likely Major High Minor Moderate Minor Moderate
CMM 2021-04 07 Report 2019, 2020, 2021, 2022 100 Rare Major Moderate Moderate Low Moderate Low
CMM 2021-04 07 Report Deadline Rare Moderate Moderate
Convention Article 23 (5) Report Deadline 2013 100 Rare Major Moderate
Convention Article 23 2 (b) Report 2016 100 Rare Major Moderate
Convention Article 23 2 (b) Report Deadline 2013, 2014, 2015, 2016 78 Likely Moderate High
Convention Article 23 2 (c) Report 2016 97 Unlikely Major High
Convention Article 23 2 (c) Report Deadline 2013, 2014, 2015, 2016 87 Moderate Moderate Moderate
Convention Article 24 (3) Implementation 2016 100 Rare Major Moderate
Convention Article 25 (2) Report 2016 100 Rare Major Moderate
Convention Article 25 (2) Report Deadline 2013, 2014, 2015, 2016 72 Likely Moderate High
Convention Article 25 (8) Report Deadline 2013 86 Moderate Major High
Data RaP MCS 44 Report Deadline 2013 82 Moderate
SciData 01 Report 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 97 Unlikely Serious High Moderate Moderate Major High
SciData 01 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 98 Unlikely Moderate Moderate Minor Low Major High
SciData 02 Report 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 98 Unlikely Serious High Moderate Moderate Moderate Moderate
SciData 02 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 97 Unlikely Moderate Moderate Minor Low Moderate Moderate
SciData 03 Report 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 99 Unlikely Serious High Serious High Moderate Moderate
SciData 03 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 99 Unlikely Moderate Moderate Major High Moderate Moderate
SciData 04 Report 2013, 2014 84 Moderate
SciData 04 Report Deadline 2013, 2014 96 Unlikely
SciData 05 Report 2013, 2014, 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022 94 Moderate Serious Severe Major High Moderate Moderate
SciData 05 Report Deadline 2013, 2014, 2015, 2016, 2017, 2018, 2019 92 Moderate Moderate Moderate Major High Moderate Moderate
SciData 07 Report 2014 100 Rare
SciData 07 Report Deadline 2014 100 Rare